Works have commenced over the past week in preparation for this project....
So whats the go with the CNG at Tuggeranong?
Going by the last tender I viewed on this, CNG facilities remain untouched.
Development application 201527584 has been lodged and closes for comment on 15 June 2015.
The plans (http://www.planning.act.gov.au/topics/your_say/comment/pubnote?sq_content_src=%2BdXJsPWh0dHAlM0ElMkYlMkZhcHBzLmFjdHBsYS5hY3QuZ292LmF1JTJGcHVibm90ZSUyRnB1Ym5vdGVEZXRhaWxfbmV3LmFzcCUzRkRBX25vJTNEMjAxNTI3NTg0JmFsbD0x) show the replacement of the underground diesel tanks with two above-ground 80 KL tanks - similar to those installed at Belconnen.
The new tanks will be sited between the sheds and the in-field carpark. (Eight spaces will be added and two removed from the carpark.)
The unloading point will be re-located to the former SNT carpark.